Acceptance Tests (W, LBT672 and FLAO)
General AIT Management Plan (by J. Brynnel)
W unit #1
W wave-front sensor laboratory acceptance test (OAA)
Acceptance test plan specification document
Acceptance test report
Closing Milestone: "W#1 ready for AO system test"
Hexapod #1 & #2
Hexapod control unit acceptance test (ADS)
Test plan specification document and test report
Acceptance test report
Closing Milestone: "HP#1/2 control units accepted"
LBT672a
Phase 1: Opto-mechanical integration (ADS)
Acceptance test plan and specification document
Acceptance test report
Closing Milestone: "LBT672a ready for shipping to Microgate"
Phase 3: Control System Integration (Microgate)
Acceptance test plan and specification document
Acceptance test report (Acceptance to be done)
Closing Milestone: "LBT672a ready for electro-mechanical tests"
Side tests. OAA software debugging and test:
OAA Software test with LBT672: first debugging session
OAA Software test with LBT672: second debugging session
Phase 4: Electro-mechanical tests at Microgate (aka AIT at Microgate) (Microgate/ADS+OAA)
Acceptance test plan specification document
Acceptance test report (Acceptance to be done)
Closing Milestone: "LBT672a ready for optical tests"
Test pogress of OAA electro-mechanical tests:
OAA electro-mechanical test: noise and stability characterization
OAA electro-mechanical test: dynamical characterization with technical shell
Phase 6:Secondary unit optical test (OAA)
Acceptance test plan specification document
Acceptance test report (Acceptance to be done)
Closing Milestone: "Flattened LBT672a shell: ready for AO tests"
FLAO
Phase 7: AO system test (OAA)
Acceptance test plan specification document
Acceptance test report (Acceptance to be done)
Closing Milestone: "AO system laboratory acceptance test passed"
W unit #2
W wave-front sensor laboratory acceptance test (OAA)
Acceptance test plan specification document
Acceptance test report (Acceptance to be done)
687f003a
: W#2 Pre Acceptance Test report
Closing Milestone: "W#2 ready for AO system test"
LBT672b
Phase 1: Opto-mechanical integration (ADS)
Acceptance test plan and specification document
Acceptance test report (Acceptance to be done)
Closing Milestone: "LBT672b ready for shipping to Microgate"
Phase 3: Control System Integration (Microgate)
Acceptance test plan and specification document
Acceptance test report (Acceptance to be done)
Closing Milestone: "LBT672b ready for electro-mechanical tests"
Phase 4: Electro-mechanical tests at Microgate (aka AIT at Microgate) (Microgate/ADS+OAA)
Acceptance test plan specification document
Acceptance test report (Acceptance to be done)
Closing Milestone: "LBT672b ready for optical tests"
Phase 6:Secondary unit optical test (OAA)
Acceptance test plan specification document
Acceptance test report (Acceptance to be done)
Closing Milestone: "Flattened LBT672b shell: ready for AO tests"
FLAO
Phase 7: AO system test (OAA)
Acceptance test plan specification document
687s002_W2_Acceptance_Test_Rev_a.pdf
: W unit 2 acceptance test report
Closing Milestone: "AO system#2 laboratory acceptance test passed"
--
ArmandoRiccardi
- 11 Nov 2007
Attachments
2
Attachments
2
I
Attachment
Action
Size
Date
Who
Comment
pdf
640a014a.pdf
manage
528 K
08 May 2007 - 17:27
ArmandoRiccardi
LBT672a Opto-Mechanical Integration Test Report
pdf
687s002_W2_Acceptance_Test_Rev_a.pdf
manage
4 MB
04 Mar 2009 - 11:37
AlfioPuglisi
W unit 2 acceptance test report
This topic: Public
>
FLAO
>
LbtAoAcceptanceTests