Horizon activities
JZ starts to work on ?? up to 8:00.
Zenith activities
After telescope is back to Zenith we perform several task in parallel:
- Reconnect cables and pipes of the LgswUnitDx that was left incomplete in August (MB)
- Recheck the alignment of the CalUnitSystemSx using the alignment mask (DP). We found a 0.3deg tilt of the beam in the vertical direction, towards the table plane. We don't know if it is due to a misalignment of M3 or the dichroic optics.
- Service the BeamCorrectorSX gears on the SX side (SR): mots are found inside the LBC box. Optics are cleaned and system is reinstalled.
- Supply power and ethernet on the LgswRack1 (JZ)
16:00 we have to handover the telescope.
We try to start the
LgswUnitDx, we have a problem with the PCD: or the amplifier is switched off or it has a wrong IP, we can't reach it.
New PatCam angles:
New Pupil motors position for IS:
Beam |
X |
Y |
Blue |
462 |
425 |
Yellow |
282 |
404 |
Red |
394 |
260 |
Check of SX CalUnit alignment
There was a tilt visible in up down direction of approximately 0.25 deg. Tertiary was move to compensate. Final position:
X | Y | Z | RX | RY | RZ | M3Tip | M3Tilt | Piston | RZ |
3.05 | -0.45 | 1.9 | -227 | -77.3 | 0 | -1315.97 | 291.009 | 0 | 0 |
However, even with this values the angle was not removed as M3 was not pistoned.
--
MarcoBonaglia - 15 Oct 2015